Sr.No |
Work Description |
Progress |
|
1 |
Main Entrance Gate |
100% |
|
2 |
Sewer Line Work |
85% |
|
3 |
Storm Water Work |
75% |
|
4 |
Rain water Harvesting |
20% |
|
5 |
Sewarage Treatment Plant Work |
25% |
|
6 |
Under Ground Water Tank Work |
20% |
|
7 |
Water Supply Work |
30% |
|
8 |
Road Work |
10% |
|
9 |
Electrical Sub-station |
5% |
|
10 |
Fire Fighting Services |
30% |
|
11 |
Laying of Cables |
5% |
|
12 |
External Developments, Street Lights, Landscaping |
10% |