Sr.No |
Towers |
Work Description |
Progress |
|
1 |
1,2,3,4,5,6,7,UGT, STP, AGANWADI, ESS, VCB ROOM, COMMERCIAL - 1, COMMERCIAL - 2, METER ROOM & VCB ROOM, GUARD ROOM |
Sub Structure Work |
100% |
|
2 |
1,2,3,4,5,6,7, STP, UGT, AGANWADI, VCB ROOM, ESS, COMMERCIAL, INTERNAL ROAD |
Super Structure Work |
100% |
|
3 |
GUARD ROOM |
Super Structure Work |
50% |
|
4 |
1 |
Finishing Work |
85% (Tile work - 93%, Putty Work - 90%, Internal Primer Work-50%, External Primer-95%) |
|
5 |
2 |
Finishing Work |
90%(Tile work - 100%, Putty Work - 90%, Internal Primer Work-90%, External Primer-95%) |
|
6 |
3 |
Finishing Work |
90%(Tile work - 100%, Putty Work - 90%, Internal Primer Work-0%, External Primer-95%) |
|
7 |
4 |
Finishing Work |
90%(Tile work - 100%, Putty Work - 90%, Internal Primer Work-0%, External Primer-95%) |
|
8 |
5 |
Finishing Work |
90%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-20%, External Primer-95%) |
|
9 |
6 |
Finishing Work |
90%(Tile work - 100%, Putty Work - 100%, Internal Primer- 0%, External Primer-95%) |
|
10 |
7 |
Finishing Work |
90%(Tile work - 100%, Putty Work - 100% , Internal primer- 0%, External primer 95%) |
|
11 |
STP |
Finishing Work |
95%(Internal Primer Work-100%) |
|
12 |
UGT |
Finishing Work |
95%(Internal Primer Work-100%) |
|
13 |
AGANWADI |
Finishing Work |
100%(Flooring-100%, glazing 100%) |
|
14 |
COMMERCIAL |
Finishing Work |
80%(Granite work- 85%, Glazing work- 60%, Aluminum louver work and false ceiling 0%) |
|
15 |
VCB ROOM |
Finishing Work |
90% |
|
16 |
ESS |
Finishing Work |
100%(Internal Primer Work-100%, External Primer-100%) |
|
17 |
INTERNAL ROAD |
Finishing Work |
100%(DBM complete) |
|
18 |
GUARD ROOM |
Finishing Work |
50%(Granite work-95%,) |