Sr.No |
Work Description |
Progress |
|
|
1 |
Main Entrance Gate Work |
5% (Foundation for Boom Barrier completed) |
|
|
2 |
Sewer Line Work |
100% |
|
|
3 |
Storm Water Work |
100% |
|
|
4 |
Rainwater Harvesting Work |
100% |
|
|
5 |
Sewarage Treatment Plant Work |
90% |
|
|
6 |
Under Ground Water Tank Work |
95% |
|
|
7 |
Water Supply Work |
100% |
|
|
8 |
Road Work |
95% |
|
|
9 |
Electrical Sub-station Work |
100% |
|
|
10 |
Laying of Cables Work |
100% |
|
|
11 |
External Developments, Street Lights, Landscaping Work |
95% |