Sr.No |
Towers |
Work Description |
Progress |
|
1 |
1,2,3,4,5,6,7 UGT, STP, ESS, VCB ROOM, COMMERCIAL-1, COMMERCIAL-2, MEATER ROOM & VCB ROOM |
Sub Structure Work |
100% |
|
2 |
GUARD ROOM |
Sub Structure Work |
60% |
|
3 |
1,2,3,4,5,6,7 UGT, STP, ESS, VCB ROOM, COMMERCIAL-A, COMMERCIAL-B, COMMERCIAL-C, AGANWADI |
Sub Structure Work |
100% |
|
4 |
1 |
Finishing Work |
85%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%, Texture-100%) |
|
5 |
2 |
Finishing Work |
85%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%, Texture-100%) |
|
6 |
3 |
Finishing Work |
85%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%, Texture-100%) |
|
7 |
4 |
Finishing Work |
85%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%, Texture-100%) |
|
8 |
5 |
Finishing Work |
80%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-0%, External Primer-100%, Texture-100%) |
|
9 |
6 |
Finishing Work |
80%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-0%, External Primer-100%, Texture-100%) |
|
10 |
7 |
Finishing Work |
30%(Tile work - 30%, Putty Work - 60%, Internal Primer Work-0%, External Primer-50%, Texture-0%) |
|
11 |
STP |
Finishing Work |
100% |
|
12 |
UGT |
Finishing Work |
100% |
|
13 |
AGANWADI |
Finishing Work |
90%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%) |
|
14 |
COMMERCIAL - A |
Finishing Work |
70% |
|
15 |
COMMERCIAL - B |
Finishing Work |
60% |
|
16 |
COMMERCIAL - C |
Finishing Work |
90% |
|
17 |
VCB ROOM |
Finishing Work |
80% |
|
18 |
ESS |
Finishing Work |
80% |
|
19 |
INTERNAL ROAD |
Finishing Work |
60%(GSB 1st Layer 85%, 2nd Layer 30%) |
|
20 |
GUARD ROOM |
Finishing Work |
0% |