Sr.No |
Towers |
Work Description |
Progress |
|
1 |
1,2,3,4,5,6 |
Sub Structure Work |
100% |
|
2 |
1 |
Super Structure Work |
100% |
|
3 |
2 |
Super Structure Work |
100% |
|
4 |
3 |
Super Structure Work |
100% |
|
5 |
4 |
Super Structure Work |
100% |
|
6 |
5 |
Super Structure Work |
100% |
|
7 |
6 |
Super Structure Work |
100% |
|
8 |
1 |
Finishing Work |
Tile work - 85%, Putty Work - 60% |
|
9 |
2 |
Finishing Work |
Tile work - 85%, Putty Work - 60% |
|
10 |
3 |
Finishing Work |
Tile work - 85%, Putty Work - 60% |
|
11 |
4 |
Finishing Work |
Tile work - 85%, Putty Work - 60% |
|
12 |
5 |
Finishing Work |
Tile work - 85%, Putty Work - 60% |
|
13 |
6 |
Finishing Work |
Tile work - 85%, Putty Work - 60% |
|
14 |
Commercial -A |
Sub Structure Work |
100% |
|
15 |
Commercial -A |
Super Structure Work |
100% |
|
16 |
COMMERCIAL & T - 7 |
Sub Structure Work |
100% |
|
17 |
COMMERCIAL & T - 7 |
Super Structure Work |
Terece Floor in Progress |
|
18 |
Commercial -C |
Sub Structure Work |
100% |
|
19 |
Commercial -C |
Super Structure Work |
100% |
|
20 |
ANGANWADI & COMMUNITY CENTER |
Sub Structure Work |
100% |
|
21 |
ANGANWADI & COMMUNITY CENTER |
|
Started |
|
22 |
UGT |
Sub Structure Work |
100% |
|
23 |
UGT |
Super Structure Work |
100% |
|
24 |
STP |
Sub Structure Work |
100% |
|
25 |
STP |
Super Structure Work |
100% |
|
26 |
VCB & LT PANEL ROOM |
Sub Structure Work |
100% |
|
27 |
VCB & LT PANEL ROOM |
Super Structure Work |
100% |
|
28 |
ESS |
Sub Structure Work |
100% |
|
29 |
ESS |
Super Structure Work |
100% |
|
30 |
METER ROOM |
Sub Structure Work |
100% |
|
31 |
METER ROOM |
Super Structure Work |
100% |