Sr.No |
Work Description |
Progress |
|
|
1 |
STP |
100% |
|
|
2 |
UGT |
100% |
|
|
3 |
ESS (Sub Structure) |
100% |
|
|
4 |
ESS (Super Structure) |
95% |
|
|
5 |
ESS (Finishing) |
10% |
|
|
6 |
Internal Central Plaza |
50% |
|
|
7 |
Storm Line |
100% |
|
|
8 |
Sewer Line |
100% |
|
|
9 |
Water Suppy Line |
100% |
|
|
10 |
Electrical Line |
50% |
|
|
11 |
Internal Roads (Subgrade) |
100% |
|
|
12 |
Internl Roads (Finishing) |
20% |
|
|
13 |
Outer 12m-Road (Subgrade) |
100% |
|
|
14 |
Outer 12m-Road (Finishing) |
95% |
|
|
15 |
Outer External Development (Finishing) |
100% |