Sr.No |
Towers |
Work Description |
Progress |
|
1 |
1,2,3,4,5,6,7, UGT, STP, ESS, VCB ROOM, COMMERCIAL-1, METER ROOM & VCB ROOM |
Sub Structure Work |
100% |
|
2 |
AGANWADI, INTERNAL ROAD, GUARD ROOM |
|
100% |
|
3 |
1,2,3,4,5,6,7, UGT, STP, ESS, VCB ROOM, COMMERCIAL-1, METER ROOM & VCB ROOM, AGANWADI |
Super Structure Work |
100% |
|
4 |
INTERNAL ROAD |
Super Structure Work |
85% |
|
5 |
GUARD ROOM |
Super Structure Work |
25% |
|
6 |
1 |
Finishing Work |
90% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-25%, External Primer-100%) |
|
7 |
2 |
Finishing Work |
95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-25%, External Primer-100%) |
|
8 |
3 |
Finishing Work |
95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-25%, External Primer-95%) |
|
9 |
4 |
Finishing Work |
95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-25%, External Primer-95%) |
|
10 |
5 |
Finishing Work |
95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-85%, External Primer-100%) |
|
11 |
6 |
Finishing Work |
95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-85%, External Primer-100%) |
|
12 |
7 |
Finishing Work |
95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-85%, External Primer-100%) |
|
13 |
STP |
Finishing Work |
100% (Railing fixing - 100%, Primer - 100%, Grating fixing - 25) |
|
14 |
UGT |
Finishing Work |
100% (Railing fixing - 100%, Primer - 100%, Grating fixing - 100%) |
|
15 |
AGANWADI |
Finishing Work |
Tile work - 100%, Putty Work - 90%, Internal Primer Work-90%, External Primer-100% |
|
16 |
COMMERCIAL - 1 |
Finishing Work |
50% (Tile work - 80%, Putty work - 75%, External Primer 80%) |
|
17 |
VCB ROOM |
Finishing Work |
75% (Flooring Work - 100%, Putty Work - 80%, External Primer - 100%) |
|
18 |
ESS |
Finishing Work |
95% (Flooring Work - 100%, Putty Work - 80%, External Primer - 100%) |
|
19 |
INTERNAL ROAD |
Finishing Work |
|
|
20 |
GUARD ROOM |
Finishing Work |
|