Sr.No |
Towers |
Work Description |
Progress |
|
1 |
1,2,3,4,5,6,7 |
Sub Structure Work |
100% |
|
2 |
1 |
Super Structure Work |
93% |
|
3 |
2 |
Super Structure Work |
100% |
|
4 |
3 |
Super Structure Work |
93% |
|
5 |
4 |
Super Structure Work |
100% |
|
6 |
5 |
Super Structure Work |
100% |
|
7 |
6 |
Super Structure Work |
100% |
|
8 |
7 |
Super Structure Work |
100% |
|
9 |
1 |
Finishing Work |
Tile fixing 90% complete |
|
10 |
2 |
Finishing Work |
Tile fixing 90% complete |
|
11 |
3 |
Finishing Work |
Tile fixing 90% complete |
|
12 |
4 |
Finishing Work |
Tile fixing 90% complete |
|
13 |
5 |
Finishing Work |
Tile fixing 90% complete |
|
14 |
6 |
Finishing Work |
Tile fixing 90% complete |
|
15 |
7 |
Finishing Work |
Tile fixing 90% complete |
|
16 |
COMMERCIAL - 1 |
Sub Structure Work |
100% |
|
17 |
COMMERCIAL - 1 |
Super Structure Work |
85% |
|
18 |
COMMERCIAL - 2 |
Sub Structure Work |
100% |
|
19 |
COMMERCIAL - 2 |
Super Structure Work |
Terrace floor in progress |
|
20 |
STP |
Sub Structure Work |
100% |
|
21 |
STP |
Super Structure Work |
100% |
|
22 |
UGT |
Sub Structure Work |
100% |
|
23 |
UGT |
Super Structure Work |
100% |
|
24 |
ESS |
Sub Structure Work |
100% |
|
25 |
ESS |
Super Structure Work |
100% |
|
26 |
VCB ROOM |
Sub Structure Work |
100% |
|
27 |
VCB ROOM |
Super Structure Work |
100% |
|
28 |
METER ROOM & VCB ROOM |
FOUNDATION WORK IN PROGRESS |
08% |