Sr.No |
Work Description |
Progress |
|
|
1 |
Main Entrance Gate Work |
Up to Plinth Level |
|
|
2 |
Sewer Line Work |
0% |
|
|
3 |
Storm Water Work |
0% |
|
|
4 |
Rainwater Harvesting Work |
0% |
|
|
5 |
Sewarage Treatment Plant Work |
0% |
|
|
6 |
Under Ground Water Tank Work |
0% |
|
|
7 |
Water Supply Work |
0% |
|
|
8 |
Road Work |
20% |
|
|
9 |
Green Area & Plantation Along Boundary Wall Work |
40% |
|
|
10 |
Milk booth Work |
Up to Plinth Level |
|
|
11 |
External Boundary Wall Work |
95% |
|
|
12 |
External Developments, Street Lights, Landscaping Work |
0% |