Construction for Urban-67A has been started and work is in progress for 10 towers. As on date we have completed Rafting and shear wall work for Tower no-12,11,10,9,8,7,6,5,4 and 3. In tower no. 12 we have completed plinth after rafting and shear wall. Shuttering for ground floor had started in tower-12.